6. The routing function in a production system-

A. manpower utilization

B. machine utilization

C. quality assurance of the product

D. optimizing material flow through the pain

Click for Answer/Explanation

Correct Answer is D

7. The determination of standard time in a complex job system is best done through-

A. stopwatch time study

B. analysis of standard data system

C. analysis of micro-motions

D. grouping timing technique

Click for Answer/Explanation

Correct Answer is B

8. Value is usually considered as a relationship between-

A. utility and cost

B. profit and cost

C. appearance and utility

D. psychology and reliability

Click for Answer/Explanation

Correct Answer is A

9. The characteristic life-cycle of a product consists of four periods. The rate of consumption increases rapidly at the beginning of the-

A. incubation period

B. decline period

C. growth period

D. maturity period

Click for Answer/Explanation

Correct Answer is C

10. The type of layout suitable for use of the concept, principles, and approaches of ‘group technology’ is-

A. Product layout

B. Cellular layout

C. Job-shop layout

D. Fixed-position layout

Click for Answer/Explanation

Correct Answer is B