26. Which one of the following activities are to be considered for production scheduling-
- Sales forecast
- Route sheet
- Time standards
- Component design
A. 2, 3 & 4
B. 1, 2 & 4
C. 2 & 4 only
D. 1, 3 & 4
27. Which one of the following is not a technique of Long-Range forecasting?
Read More- GATE Mechanical Engineering Quiz-01
A. Delphi
B. Collective Opinion
C. Correlation and Regression
D. Market research and market survey
28. In ABC analysis, A item requires-
A. No safety stock
B. Low safety stock
C. High safety stock
D. Moderate safety stock
29. What information do the Gnatt Charts provide us?
A. Production Schedule
B. determining the selling price
C. Break Even Point Analysis
D. None of the Above
30. Who is the father of Industrial Engineering?
A. Fredrick Winslow Taylor
B. Jack Gilbert
C. H. L. Gantt
D. None of the Above
We will soon update more Industrial Engineering Objective Questions and Answers