16. Dummy activities are used in a network to-
A. facilitate computation of slacks
B. avoid the use of resources
C. satisfy precedence requirement
D. determine project completion time
17. Classifying items in A, B and C categories for selective control in inventory management is done by arranging items in the decreasing order of-
A. Annual usage value
B. Item value
C. Item demand
D. total inventory costs
18. The aim of value engineering is to-
Read More- Physical Quantities and Measurements Short Notes
A. determine the selling price of a product
B. minimize the cost without a change in the quality of the product
C. find the depreciation value of a machine
D. All the above
19. Which of the following hand-motion belongs to ‘Therbligs’ in motion study-
- Unavoidable delay
- Preposition
- Select
- Reach
A. 1 and 4
B. 1, 2 and 3
C. 2, 3 and 4
D. 1 and 2
20. The variance of the completion time for a project is the sum of the variance of-
A. All activity times
B. Critical activity times
C. Non-critical activity times
D. Activity times of first and the last activities of the project